Anambra House of Assembly expresses concern over poor infrastructures by contractors

0

The Anambra state House of Assembly Committee on Economic Planning , sustainable Development Goals and Donor Agencies have expressed worry over the poor level of work done by contractors handling the construction of six hundred fish ponds , hostel blocks and farm houses in Aguleri and Adazi Nnukwu communities.
To this end the committee says it may be inviting the Commissioner for Agriculture, Mr Nnamdi Onukwuba to appear before the State house to explain how his ministry expended the One point Five billion naira agricultural loan received from the Central Bank of Nigeria in 2020.

The Chairman of the Committee, Mr Ebere Ejiofor stated this shortly after he led other members of the committee to oversight some of the projects awarded by the state government.
Our Correspondent reports that the law makers threatened to call for the revocation of the contracts following the slow pace and quality of work done in the two communities visited.

The Central Bank of Nigeria (CBN) launched guidelines for the regulation of the Private Sector-Led Accelerated Agriculture Development Scheme (P-AADS), in order to boost private sector staple food production, industrial raw materials and support food security, job creation and economic diversification in the country in 2020.

The apex bank said in the bid to address food security and youth unemployment challenges across the country, the Accelerated Agriculture Development Scheme (AADS) is to engage 370,000 youths in agricultural production, in collaboration with state governments.

In line with this , the Anambra state government under the leadership of Governor Willie Obiano applied and collected One point five billion naira for the sole purpose of fish and rice farming in some local government areas across the three senatorial zones of the state.

Contracts were awarded through the state ministry of Agriculture for the construction of three hundred fish ponds in Adazi Nnukwu in Anaocha local government area to the tune of seventy five million , two hundred as fifty thousand naira and another three hundred fish pond in Aguleri, Anambra East local government area to the same amount of seventy five million, two hundred and fifty thousand naira.

ALSO READ  FG will support you - VP Osinbajo promise repentant Boko Haram

Contract was also awarded for the construction of fifty bed capacity hotel each in Aguleri and Adazi Nnukwu communities to the tune of one hundred and thirteen million five hundred and five thousand naira.
Farm houses , entrance gates, perimeter fencing, and generator houses was also awarded for the two communities with a total amount of one hundred and twenty two million , one hundred and seventy nine thousand, two hundred and eighty five kobo.
A document made available to the House committee by the Ministry of Agriculture, also shows that forty one million , seven hundred and sixty three thousand naira was also awarded for the construction of industrial boreholes to serve the two fish farm ponds.
As part of its responsibility , the House committee on Economic Planning, SDG and Donor agencies decided to embark on oversight function to ascertain the level and quality of work done on the project which involves tax payers money.
The Chairman of the Committee ,Mr Ebele Ejiofor, ( member, representing Anaocha constituency 1), after visiting the project sites expressed displeasure over the work on ground which he said was not commiserate with the amount so far released to the firms.

He regretted that the sum of three hundred and twenty six million , one hundred and thirty six thousand , six hundred and three naira had been paid to contractors , out of five hundred and ten million , three hundred and twenty thousand , two hundred and eighty five naira being total sum of the projects in Aguleri and Adazi Nnukwu.

"This is a total failure, there is nothing to show that this amount of money have been released. Look at Adazi Nnukwu site, only one hundred and  fifty fish ponds have been done and its not properly done,the work is not durable,they are using red mud to plaster walls of the generating  house while that of Aguleri fifty bed hotel is still at foundation, and yet millions of naira have been released as claimed by the Commissioner for Agriculture . I think we will invite him to come and explain how such amount will be released with little or nothing to show on ground ".

Another member of the committee Mr Emmanuel Nwafor representing Orumba South constituency, described the quality of work as substandard and called for the revocation of the contracts which he said was for the interest of the masses.
” From what we have on paper, they said forty percent of the work have been completed but what we are seeing here , the 300 bed capacity hostel is still under the ground, they have not even come to the DPC level, so I believe the Commissioner for Agriculture should be called to order so that he can answer some certain questions. We require the Commissioner to give us details of what have been going on, this project is suppose to have have been handed over to the people of Anambra state but look at where we are “

ALSO READ  Electricity Consumers praise CBN for multi-billon naira power intervention

In an interview, the Managing Director , Anambra state Fisheries and Aquaculture Development Agency FABDA , Mr Emeka Iloghalu describe the projects as life serving and a well thought out government project but however expressed worry over the delay in the completion of the youth friendly initiative .
According to him, ” FABDA is suppose to be the consultant to this project, FACDA made the Concept, design and structuring of the project. And according to the guideline of the CBN, the project management team was set up by His Excellency the governor of Anambra state and all the work was done. We supposed to have finished but at the moment the Ministry of Agriculture , Honorable Commissioner and the Permanent Secretary are in the best position to provide the details of why this project is still at this stage.”

ALSO READ  Ohanaeze disclaims statement on re-arrest, re-arraignment of Nnamdi Kanu

Our correspondent spoke with Mr Chukwudi Okosie , Site Supervisor for CIVIL CREST Engineering Services Ltd, one of the contractors handling the construction of the fish ponds in Agulerj , Farm Houses, entrance gates , fencing and generator houses in Adazi Nnukwu and Aguleri who said though he don’t have the details of the amount so far received , the project would be delivered in the next four months.
” I don’t actually have details for the amount of money that have been released, so I can’t compare if work on ground is up to the money but I believe we have been doing well, our challenges are, during the rainy season, the road was too bad that sometimes we get stuck , to come down here becomes a problem, at times we won’t even do any work, getting materials and bringing workers here is the main challenge we have. Secondly the nature of this place, the floor was so bad that we could not get materials through especially at the back where we needed to put fence.

Contract was also awarded for the provision of two 75KVA power Generating sets for the two fish ponds in the communities to the tune of twenty three million naira .